By Dana Amihere, dana@marylandreporter.com
ANNAPOLIS—The Board of Public Works on Wednesday asked the the states wetlands administration to explain the high compensation rates of $175 per square foot proposed for three Cordish Power Plant restaurants in Baltimores Inner Harbor Hard Rock, Dicks Last Resort and Phillips Seafood.
The establishments wetlands licenses include fees charged by the state for use of the Patapsco River diverted from its intended use as navigable waters, and for the direct impact the licensees activities will have on the aquatic environment.
The licensing items were officially withdrawn from consideration at this weeks meeting by the executive secretary of the Board of Public Works, Sheila McDonald. But Comptroller Peter Franchot insisted on debating the fairness of the confiscatory rates charged to install a roof over the eating and bar area of an existing pier.
Assessing a rate of $175 per square foot is obviously ridiculous, Franchot said, and would essentially be a non-starter, noting that the highest rate hed ever heard of for a similar use in Annapolis was $132 per square foot.
An alternate appraisal of $110 per square foot for the value of the over-water rights had been presented to the Maryland Environment Department, but the department chose the higher appraisal.
At about 4,500 square feet, Phillips Seafood has the largest pier and would owe nearly $780,000 above and beyond the projects construction costs.
Why should state agencies pull this out of of these businesses? Franchot asked. I understand budgets are tight and I guess that theyre looking to beef up their own general fund, but this is clearly not acceptable.
Gov. Martin OMalley noted that its within the Boards discretion to reduce the fee, or as in the case of Maryland Broadband in 2008, charge nothing at all for putting in cabling across a state bridge.
Treasurer Nancy Kopp questioned the legality of the projects citing legislation which prohibits structures from being built on piers. OMalley noted that exceptions to those laws can be granted, and characterized the renovation projects as creating floating restaurants,
No decision was made on the proposed licensing fees. The board asked Wetlands Administrator Doldon Moore to come back with some answers in two when the items would be put back on the agenda for discussion and a vote.